Excavator Work beginning at Joshua Slocum Road
Straight magenta line Wilderness Area Boundary (MapSource version only)
Straight green line private property boundary (MapSource version only)
Black section - original cut path
Total Length of original cut path - 3.3 km

Day 1 & 2, August 2 & 3 - dark red section (starting from Joshua Slocum end on right, east)
Day 3, August 9 - green section
Day 4, August 16 - gold section
Day 5 & 6, August 17 & 18 - dark blue section
Day 7 & 8, August 19 & 20 - dark magenta section
Day 9 & 10, August 21 & 22 - cyan section
Day 11 & 12, August 25 & 26 - light grey section
Day 13, August 27 - red section
Day 14 & 15, August 29 & 30 - blue section
Day 16, September 7 - dark red section
Day 17, September 11 - dark green (from hwy 3, Tantallon end on left, west)
Day 18, September 13 - dark blue (from Tantallon end)
Day 19, September 15 - dark magenta (from Tantallon end)
Day 20 & 21, September 17 & 18 - dark cyan (from Tantallon end)
Day 22, September 19 - red (from Tantallon end)
Day 23, September 20 - green (from Tantallon end)
Day 24, September 21 - blue (from Tantallon end) TRAIL SECTIONS LINKED
Day 25, September 24 - excavator/bobcat work begins to improve trail
TRAIL SECTIONS LINKED
September 21, 2012 - Work Day 24
Thank you to Dave Dorey for many hours of excavating.
Thanks to Mike Marriott for guiding project and excavator work.